Disclaimer: Please note that all dates, timelines and anticipated work noted below is subject to change without notice and is to be viewed as informed estimations only made as of April 9, 2026.
Development History
September 9, 2025 – City Council Approved the Sale of the Property to the MDC.
March 5, 2026 – Joint Venture (JV) Partner/Purchaser Identified
Current Use of Land
Parking lot leased by the City
Future Property Information
Unknown at current time. Discussions ongoing with vetted JV Partner/Purchaser.
Completed Work and Expected Milestones 2026 (subject to change)
Q1
Q2
Q3
Q4
Preferred JV/Purchaser identified
ESA 1, 2 and geotechnical for RSC started
Property survey started
Due diligence paid (Split 50/50 – MDC and the preferred JV/Purchaser
R-Plan to be added to title
ESA 1, 2 and geotechnical to be completed
JV / Sale to be brought to the Board/City Council for approval
JV/Sale completed
Pre-Con meeting
Site Plan to be submitted
RSC to be completed
Site Plan approved
Building Permit submitted
Construction financing to be arranged
Q1
Preferred JV/Purchaser identified
ESA 1, 2 and geotechnical for RSC started
Property survey started
Due diligence paid (Split 50/50 – MDC and the preferred JV/Purchaser
Q2
R-Plan to be added to title
ESA 1, 2 and geotechnical to be completed
JV / Sale to be brought to the Board/City Council for approval
Q3
JV/Sale completed
Pre-Con meeting
Site Plan to be submitted
RSC to be completed
Q4
Site Plan approved
Building Permit submitted
Construction financing to be arranged
Glossary of Common Development Terms & Acronyms
APS: Agreement of Purchase and Sale CIP: Community Improvement Plan CMHC: Canadian Mortgage Housing Corporation CMLI: CMHC Multi-Unit Loan Insurance ESA: Environmental Site Assessment JV: Joint Venture Pre-Con: Pre-Construction Meeting with City Planning Dept. R-Plan: Registered Plan RSC: Record of Site Condition T/O Financing: Take-out Financing (payout construction financing) VTB: Vendor Take-Back