January 27, 2025 – City Council approved the sale of the property to the MDC.
September 22, 2025 – APS and VTB was approved by the Shareholder.
Current Use of Land
8 Gale Crescent – land is currently vacant, surrounded by City owned protective fencing.
8 Gale Crescent was previously the site of the Garden City Arena Complex.
29 Riordon Street – former City parking lot leased by Niagara Regional Housing (NRH) for temporary housing-focused shelter. NRH has been informed lease will not be renewed.
Future Property Information
More than 800 residential units.
Approximately 200 parking spaces
25% of units to be affordable as per CMHC/CMLI Select Program.
Completed Work and Expected Milestones for 2026 (subject to change)
Q1
Q2
Q3
Q4
Pre-Con for Site Plan completed
Due Diligence period is Extended
Purchaser starts Site Plan, Building Permit & Rezoning
Progress monitored
Purchaser continues Due Diligence
Monitor Progress
Due Diligence extension expires
Purchaser continues due diligence
Riordon Lease with Niagara Regional Housing expires
Q1
Pre-Con for Site Plan completed
Due Diligence Period is Extended
Purchaser starts Site Plan, Building Permit & Rezoning
Q2
Progress monitored
Purchaser continues Due Diligence
Q3
Monitor Progress
Due Diligence extension expires
Purchaser continues due diligence
Q4
Riordon Lease with Niagara Regional Housing expires.
Glossary of Common Development Terms & Acronyms
APS: Agreement of Purchase and Sale CIP: Community Improvement Plan CMHC: Canadian Mortgage Housing Corporation CMLI: CMHC Multi-Unit Loan Insurance ESA: Environmental Site Assessment JV: Joint Venture Pre-Con: Pre-Construction Meeting with City Planning Dept. R-Plan: Registered Plan RSC: Record of Site Condition T/O Financing: Take-out Financing (payout construction financing) VTB: Vendor Take-Back