Disclaimer: Please note: All dates, timelines and anticipated work noted below is subject to change without notice and is to be viewed as informed estimations only made as of April 9, 2026
Development History
January 27th, 2025 – City Council approved the sale of of the property to the MDC.
September 22, 2025 – Shareholders approved Joint Venture (JV) and Shareholder Loan.
Current Use of Land
Unoccupied former City Facility
Was previously used for St. Catharines Fire Prevention
Existing Building will be demolished as part of development
Expected Property Information
30 Residential Rental Units
14 Parking Spaces
25% of units to be affordable under CMHC as per CMLI Select Program
Completed Work and Expected Milestones 2026 (subject to change)
Q1
Q2
Q3
Q4
Demolition Permit received
Pre-Con completed
Construction financing secured
Site Plan / CIP submitted (April 7)
Demolition
Building Permit Issuance
Building construction commences at factory
Construction continues at factory and on-site
Submit CMHC/CMLI application
Completion of construction at factory and on-site
Occupancy Permit obtained
CMHC/CMLI T/O Financing to be secured.
Q1
Demolition Permit received
Pre-Con completed
Construction financing secured
Site Plan / CIP submitted (April 7)
Q2
Demolition
Building Permit Issuance
Building construction commences at factory
Q3
Construction continues at factory and on-site
Submit CMHC/CMLI application
Q4
Completion of construction at factory and on-site
Occupancy Permit obtained
CMHC/CMLI T/O Financing to be secured.
Glossary of Common Development Terms & Acronyms
APS: Agreement of Purchase and Sale CIP: Community Improvement Plan CMHC: Canadian Mortgage Housing Corporation CMLI: CMHC Multi-Unit Loan Insurance ESA: Environmental Site Assessment JV: Joint Venture Pre-Con: Pre-Construction Meeting with City Planning Dept. R-Plan: Registered Plan RSC: Record of Site Condition T/O Financing: Take-out Financing (payout construction financing) VTB: Vendor Take-Back