Disclaimer: Please note that all dates, timelines and anticipated work noted below is subject to change without notice and is to be viewed as informed estimations only made as of April 9, 2026.
Development History
September 9, 2025 – City Council approved the sale of property to the MDC.
February 12, 2026 – Joint Venture (JV) / Purchaser Identified.
Current Use of Land
Parking lot leased by the City
Future Property Information
Unknown at current time. Discussions ongoing with a vetted JV Partner / Purchaser
Completed Work and Expected Milestones for 2026 (subject to change)
Q1
Q2
Q3
Q4
Preferred JV / Purchaser Identified
Ordered ESA 1, 2 and Geotechnical for RSC
Property survey ordered
Applied for Federal Development Funding.
ESA 1, 2 and Geotechnical to be completed
JV / Sale to brought to Board / Council for approval
JV / Sale completed
Pre-Con meeting
Site Plan to be submitted
Site Plan Approved
Building Permit submitted
Construction Financing to be arranged.
Q1
Preferred JV / Purchaser Identified
Ordered ESA 1, 2 and Geotechnical for RSC
Property survey ordered
Applied for Federal Development Funding.
Q2
ESA 1, 2 and Geotechnical to be completed
JV / Sale to brought to Board / Council for approval
Q3
JV / Sale completed
Pre-Con meeting
Site Plan to be submitted
Q4
Site Plan Approved
Building Permit submitted
Construction Financing to be arranged.
Glossary of Common Development Terms & Acronyms
APS: Agreement of Purchase and Sale CIP: Community Improvement Plan CMHC: Canadian Mortgage Housing Corporation CMLI: CMHC Multi-Unit Loan Insurance ESA: Environmental Site Assessment JV: Joint Venture Pre-Con: Pre-Construction Meeting with City Planning Dept. R-Plan: Registered Plan RSC: Record of Site Condition T/O Financing: Take-out Financing (payout construction financing) VTB: Vendor Take-Back